The project here and now
In June 2011, the construction of Mediaspace will commence in earnest.
Wednesday 8 June 2011 we officially cut the first sod for the large structure, which during the coming four years will transform the southern bastion of the harbour from commercial harbour to vibrant urban space.
Completion of main project
Parallel with the first phase of construction we complete the main project.
The main project includes detailed planning of number of themes - among others:
- Selection of materials
- Lighting and light design
- Acoustics
- Decoration
- Accessibility
- Design
- Dynamic surfaces
- Facades
- Indoor climate
- Traffic patterns in the car park
- Planting
- Decor and equipment for the open spaces
Timetable
Below, you can see the overall timetable for the project.
2011-2015
- Main project design
- Execution
- Citizen and user involvement
- Development of services and activities in Mediaspace
- End of 2014: Mediaspace is finished
- End of 2015: Waterfront spaces and opening of the river are finished
2009-2010
- Winner of the project competition selected
- Development of architecture and functions
- Project design and processing of the project
- Enterprise tender
- Citizen and user involvement
2008
- Project competition
- Tender following negotiation
- Further development of services and activities in Mediaspace
- Citizen and user involvement
2006-2007
- Preparation of the process
- Citizen and user involvement
- Drawing up competition program
- Development of network and cooperation
2005-2006
- Development of ideas and planning of the process
- Establishing core values for the project
- Establishing the framework for competition and tender
Citizen and user involvement
In the various phases of the project, involvement of citizens and users takes place continuously.
Read more about the project’s involvement processes